FYI I am just trying to save 173 hours.
Sl.No | Tasks | Time Required Per VM (Minutes) | Time required for total 200 VMs (Minutes) | Time required for total 200 VMs Per Tasks (Hours) |
1 | Moving The VMs to the transport Datastore | 10 | 2000 | 33.33 |
2 | Power off the VM | 5 | 1000 | 16.67 |
3 | Unregister the VM from Source vCenter 4.0 | 2 | 400 | 6.67 |
4 | Reregister the VM in the destination vCenter | 2 | 400 | 6.67 |
5 | Changing the VM Network to DHCP VLAN (Say VLAN 15) | 2 | 400 | 6.67 |
6 | Powering on the VM | 3 | 600 | 10.00 |
7 | Upgrade the VMware tools | 5 | 1000 | 16.67 |
8 | Reboot the VM | 2 | 400 | 6.67 |
9 | shutting down the VM’s to upgrade the VM hardware version | 2 | 400 | 6.67 |
10 | Upgrade the VM hardware version | 2 | 400 | 6.67 |
11 | Powering on the VM | 3 | 600 | 10.00 |
12 | Reboot again it if the hardware upgrade requires reboot | 2 | 400 | 6.67 |
13 | ipconfig/release and Ipconfig/renew | 2 | 400 | 6.67 |
14 | Move the VM from Transport LUN to the Normal VMFS datastore | 10 | 2000 | 33.33 |
16 | Total Time | 52 | 10400 | 173.33 |